The Cayman Islands' leading construction company.
All rights reserved | Credits
This project included transforming a hair salon into two separate office spaces separated by a fire rated demising wall.
The scope of works included the erection of a new, fully functional office kitchen, a conference room, and new bathrooms in both
offices. Troffer lighting fixtures were removed and replaced with LED wafers to give the office a cleaner and more updated finish.
- Demolition of existing hair salon on 2nd floor
- Fit-out of 1,800 square foot office space
- Upgraded Mechanical Systems
- New Plumbing systems including kitchenette
- New Sanitary distribution for kitchenette
- Custom millwork expansion of building footprint
Client Representative: Warren Greene Ltd.
Start Date: December 2017
Duration: 4 weeks
Forecast Completion Date: December 2017
Delivered on time