Caribbean Club
Residential & Hospitality

Caribbean Club

Porte Cochere Works

The Porte Cochere construction required the building of a leveled foundation at an accurate height to facilitate the installation of off-island prefabricated steel work. All embedments were surveyed and were specifically positioned for steel erection.

The roof of the Porte Cochère was built using an upstand beam with hidden drainage inside the columns, through which rainwater is recycled for watering the surrounding plants. A new driveway made of carefully laid pavers completed this front entrance 09 renovation.

Key quantitied and scope fo work

- Front entrance construction on the #1 hotel on TripAdvisor in the Cayman Islands
- Completed with minimum disruption to hotel guests and West Bay Rd. traffic
- Coordinated and installed foundations across an active driveway that tied into the existing building’s substructure
- Formed and poured concrete beams at height in difficult areas of
access

Client Representative: Danielle Wolfe
Start Date: August 2017 & 2018
Duration: 4 months
Completion Date: November 2017 & 2018
Delivered on time